It is a pleasure to serve with you in the Chair, Mr Twigg. In the last sitting, we discussed the various clauses and Government amendments in this group, and I thank hon. Members on both sides of the Committee for their considered engagement with them. The proposed changes we are considering are, without question, a significant evolution of the nationally significant infrastructure projects regime, and it is entirely right and proper that they are subject to intensive scrutiny.
As the Committee is aware, I set out the Government’s position on this matter in considerable detail in my written ministerial statement from 23 April. I therefore intend to focus my remarks on providing useful further points of clarification about the rationale for the proposed reforms and how we see the system operating once they have been made.
In her remarks, the hon. Member for North Herefordshire conceded that the NSIP process can take a long time, but she implied that the problem was merely confined to individual applications. The Government disagree. From our perspective, the problem that these and other changes in this chapter are intended to remedy are systemic. The status quo is not working, and all too often it is burdensome to applicants and consultees alike.
We know that the performance of the NSIP regime as a whole has deteriorated sharply over recent years. We know that pre-application periods have, on average, nearly doubled since 2013, increasing from over 14 months to nearly 28 months in 2021. As much as Labour Members welcome any and every reminder of the chaos unleashed under recent Conservative Administrations, I do not believe that the deterioration we are discussing can be attributed to the uncertainty that the post-2016 period engendered.
The evidence clearly points to the fact that inefficiencies in the NSIP system, both structural and cultural, are driving delays and high costs. We heard examples this morning of the fact that the documentation underpinning consents has been getting longer, and in too many instances now runs to tens of thousands of pages. Part of the reason is that the statutory and prescriptive nature of the pre-application requirements—I again remind the Committee that they are absent from other planning regimes, including those used for applications for new housing—are driving perverse outcomes.
It is precisely because the requirements are statutory that applicants fear that falling short of them will see their project rejected further down the line, or leave them exposed to judicial review. As we have discussed, the result is that projects are slowed down as developers undertake ever more rounds of consultation and produce greater amounts of documentation to ensure that the requirements are met. Sensible improvements are deterred because applicants worry that they will require further rounds of consultation to insulate them from challenge.
In short, as I argued in the previous sitting, the dynamics of the system are actively encouraging risk aversion and gold-plating and are compelling applicants to go above and beyond what may be required in law, rather than merely ensuring that an application is acceptable in planning terms. Because the root of the problem is the statutory nature of the requirements, it is worth noting that the same behavioural incentives would be in play if we reinserted into the Bill precise statutory criteria for what constitutes effective consultation, as the hon. Member for Taunton and Wellington suggested we should.
In his contribution, the shadow Minister argued that we should focus on improving rather than removing the statutory requirements in question. However, he overlooked the fact that the NSIP action plan, published by the previous Government in February 2023, contained a range of reforms designed to drive more effective and proportionate approaches to consultation and engagement, including new cost-recoverable pre-application services for applicants at the Planning Inspectorate, and revised and strengthened pre-application guidance.
While those steps were welcome, and this Government are seeking to embed new services and cost-recovery mechanisms, the feedback we have received from a wide range of stakeholders suggests that they will not deliver the necessary step change needed to tackle risk aversion and gold-plating. It is the dynamic that has arisen as a result of the very existence of the statutory pre-application requirements in question that is hampering their nominal purpose of producing better outcomes, and the present arrangements are driving up costs not only for developers, but for the bill payers and taxpayers we all represent.
The Government are in complete agreement with the hon. Member for North Herefordshire that early, meaningful and constructive engagement with those affected, including local authorities, statutory consultees, landowners and local communities, often leads to better schemes, greater local benefits and improved mitigation. We still want and expect the NSIP regime to function on the basis of a front-loaded approach in which development proposals are thoroughly scoped and refined prior to being submitted to the Planning Inspectorate. As part of that process, we still want and expect high-quality, early, meaningful and constructive engagement to take place and for positive changes to be made to applications. However, we want and expect it to take place without the downsides that the current statutory requirements are causing.
Removing the statutory requirements in question does not signify that pre-submission consultation and high-quality engagement is no longer important. Statutory guidance that the Government will be required to produce will encourage such pre-application engagement and consultation, but with applicants given the flexibility to carry it out in the way that they consider best for their proposed development, in accordance with that guidance.
Equally as importantly, the system will still reward high-quality engagement and consultation. The Planning Inspectorate will continue to assess whether applications are suitable to proceed to examination. We expect guidance to emphasise that without adequate engagement and consultation, applications are unlikely to be able to do so. Guidance and advice from the Planning Inspectorate will be aimed at helping applicants demonstrate that they are of a satisfactory standard in terms of meeting that process.
Ultimately, all communities will still be able to have their voices heard, whether that is through objecting outright to applications or providing evidence of adverse impacts through the post-submission examination process, which all applications obviously still need to go through.